Questões de Concurso Público METRÔ-SP 2014 para Analista Desenvolvimento Gestão Júnior - Economia
Foram encontradas 60 questões
I. os passageiros que descem na estação Chuva, descem na terceira estação após os passageiros que descem na estação Vento.
II. os passageiros que descem na estação Brisa, descem antes do que os passageiros que descem na estação Água e também os que descem na estação Vento.
III. a estação Terra não é a estação central das cinco estações.
Dos 500 passageiros que embarcaram no trem na estação inicial, 35% desceram em Água, 12% desceram em Brisa, 32% desceram em Chuva, 10% desceram em Terra e 11% desceram em Vento. Assim, pode-se concluir corretamente que, dos 500 passageiros que embarcaram no trem na estação inicial, ainda restam no trem, após a estação Água, um número de passageiros igual a :
September 4, 2013
By Greg Aragon
Tunneling 100 ft below a busy city with varying substructure is a delicate job, especially when the work comes .....A.... 8 ft of existing tunnels. Such is the case on San Francisco's new $1.5-billion Central Subway Project, which began major subterranean excavation last month.
"The tunnels pass through both soft ground and Franciscan formation, which is heterogeneous rock that is not predictable except in its unpredictability," says Sarah Wilson, a San Francisco Municipal Transportation Agency (SFMTA) resident engineer.
While underground conditions will be tricky, the project's twin earth-pressure-balance tunnel-boring machines will be able to adjust their blades and cut through any sand, dirt or rock, says Wilson. The TBMs, dubbed Mom Chung and Big Alma, are each 350 ft long and weigh 750 tons.
Mom Chung was first out of the 450-ft-long launch box. Over the next 10 months, she will travel north, creating a 1.7-mile-long tunnel. Big Alma will begin digging a southbound parallel tunnel later this month.
The tunnels are the main component of the Central Subway Project, which is extending the Muni Metro T Third Line through one of the most densely populated neighborhoods in the U.S. with three new underground stations and one at street level. Work on the line is scheduled to wrap up in 2019.
To prevent and control ground and adjacent structure settlement, the team will use compensation grouting, in which a horizontal array of grout pipes is installed into a shaft drilled down next to the tunnel alignment. "We are basically preconditioning the ground and making it homogeneous so that there are no surprises for the crossing," says John Funghi, SFMTA program director.
September 4, 2013
By Greg Aragon
Tunneling 100 ft below a busy city with varying substructure is a delicate job, especially when the work comes .....A.... 8 ft of existing tunnels. Such is the case on San Francisco's new $1.5-billion Central Subway Project, which began major subterranean excavation last month.
"The tunnels pass through both soft ground and Franciscan formation, which is heterogeneous rock that is not predictable except in its unpredictability," says Sarah Wilson, a San Francisco Municipal Transportation Agency (SFMTA) resident engineer.
While underground conditions will be tricky, the project's twin earth-pressure-balance tunnel-boring machines will be able to adjust their blades and cut through any sand, dirt or rock, says Wilson. The TBMs, dubbed Mom Chung and Big Alma, are each 350 ft long and weigh 750 tons.
Mom Chung was first out of the 450-ft-long launch box. Over the next 10 months, she will travel north, creating a 1.7-mile-long tunnel. Big Alma will begin digging a southbound parallel tunnel later this month.
The tunnels are the main component of the Central Subway Project, which is extending the Muni Metro T Third Line through one of the most densely populated neighborhoods in the U.S. with three new underground stations and one at street level. Work on the line is scheduled to wrap up in 2019.
To prevent and control ground and adjacent structure settlement, the team will use compensation grouting, in which a horizontal array of grout pipes is installed into a shaft drilled down next to the tunnel alignment. "We are basically preconditioning the ground and making it homogeneous so that there are no surprises for the crossing," says John Funghi, SFMTA program director.
September 4, 2013
By Greg Aragon
Tunneling 100 ft below a busy city with varying substructure is a delicate job, especially when the work comes .....A.... 8 ft of existing tunnels. Such is the case on San Francisco's new $1.5-billion Central Subway Project, which began major subterranean excavation last month.
"The tunnels pass through both soft ground and Franciscan formation, which is heterogeneous rock that is not predictable except in its unpredictability," says Sarah Wilson, a San Francisco Municipal Transportation Agency (SFMTA) resident engineer.
While underground conditions will be tricky, the project's twin earth-pressure-balance tunnel-boring machines will be able to adjust their blades and cut through any sand, dirt or rock, says Wilson. The TBMs, dubbed Mom Chung and Big Alma, are each 350 ft long and weigh 750 tons.
Mom Chung was first out of the 450-ft-long launch box. Over the next 10 months, she will travel north, creating a 1.7-mile-long tunnel. Big Alma will begin digging a southbound parallel tunnel later this month.
The tunnels are the main component of the Central Subway Project, which is extending the Muni Metro T Third Line through one of the most densely populated neighborhoods in the U.S. with three new underground stations and one at street level. Work on the line is scheduled to wrap up in 2019.
To prevent and control ground and adjacent structure settlement, the team will use compensation grouting, in which a horizontal array of grout pipes is installed into a shaft drilled down next to the tunnel alignment. "We are basically preconditioning the ground and making it homogeneous so that there are no surprises for the crossing," says John Funghi, SFMTA program director.
News release issued at 3:27 pm, October 6, 2013.
The investigation into the cause of a fatal overnight construction accident on the Red Line in Washington, D.C. is ....B.... . The investigation team, led by Metro's Chief Safety Officer, has authorized the release of the following facts and preliminary findings:
The incident occurred shortly after midnight, Sunday, October 6, 2013, in a work zone on the outbound (Glenmont direction) track between Union Station and Judiciary Square.
Contractors and WMATA employees were performing rail renewal, a process that involves removing old sections of rail, installing new sections of rail and related activity such as welding and grinding.
At approximately 12:03 a.m., there was a fire and loud noise that originated near heavy track equipment used to weld rail sections together into a continuous strip.
The fire and loud noise originated approximately 70 to 80 feet from the injured workers. The root cause of the fire/noise has not yet been determined. It is not yet known if there was a fluid leak or another mechanical issue.
The fire was extinguished by workers using a handheld fire extinguisher.
The incident caused a 40-foot section of rail to move, striking three workers (two WMATA employees and a contractor). It is not yet known what caused the piece of rail to move.
The two WMATA employees - one track worker and one supervisor - suffered serious but non-life-threatening injuries from being struck by the piece of rail. They were transported to local hospitals.
The contractor, an employee of Holland Co., was fatally injured as a result of being struck by the piece of rail.
News release issued at 3:27 pm, October 6, 2013.
The investigation into the cause of a fatal overnight construction accident on the Red Line in Washington, D.C. is ....B.... . The investigation team, led by Metro's Chief Safety Officer, has authorized the release of the following facts and preliminary findings:
The incident occurred shortly after midnight, Sunday, October 6, 2013, in a work zone on the outbound (Glenmont direction) track between Union Station and Judiciary Square.
Contractors and WMATA employees were performing rail renewal, a process that involves removing old sections of rail, installing new sections of rail and related activity such as welding and grinding.
At approximately 12:03 a.m., there was a fire and loud noise that originated near heavy track equipment used to weld rail sections together into a continuous strip.
The fire and loud noise originated approximately 70 to 80 feet from the injured workers. The root cause of the fire/noise has not yet been determined. It is not yet known if there was a fluid leak or another mechanical issue.
The fire was extinguished by workers using a handheld fire extinguisher.
The incident caused a 40-foot section of rail to move, striking three workers (two WMATA employees and a contractor). It is not yet known what caused the piece of rail to move.
The two WMATA employees - one track worker and one supervisor - suffered serious but non-life-threatening injuries from being struck by the piece of rail. They were transported to local hospitals.
The contractor, an employee of Holland Co., was fatally injured as a result of being struck by the piece of rail.
- A Cia. Alfa adquiriu 30% das ações da Cia. Epsilon, passando a ter influência significativa na administração.
- A Cia. Beta é uma empresa comercial e adquiriu máquinas especiais para revender.
- A Cia. Gama adquiriu máquinas especiais que serão utilizadas em seu processo produtivo.
- A Cia. Delta adquiriu um lote de ações da Cia. Mega e pretende negociá-las a qualquer momento, quando houver necessidade de recursos financeiros.
Os ativos adquiridos pelas Cias. Alfa, Beta, Gama e Delta são classificados no Balanço Patrimonial das respectivas empresas no Ativo
Pensador Contribuição teórica para
o pensamento econômico
I. Adam Smith 1. quase-renda
II. David Ricardo 2. divisão do trabalho
III. John Keynes 3. propensão marginal a consumir
IV. Alfred Marshall 4. vantagens comparativas
Pensador e contribuição teórica para o pensamento econômico estão corretamente correlacionados em:
A eficácia da política monetária em controlar a demanda agregada pode variar
PORQUE
em um país que possui dívida pública com vencimento no curto prazo, ou indexada pela taxa de juros de curto prazo, alterações nas taxas de juros não produzem mudanças no valor de mercado do estoque da dívida, provocando um efeito-riqueza. É correto afirmar:
O texto acima refere-se
NÃO reflete algum tipo de conflito entre objetivos ma- croeconômicos:
Operação realizada por um país Rubrica de Conta
1. investimento direto I. conta capital
2. bens não financeiros não produzidos
− cessão de marcas e patentes II. conta de serviço e rendas
3. aluguel de equipamentos III. balança comercial
4. viagens internacionais IV. conta financeira
As corretas correlações entre a operação realizada por um país e a rubrica de contas às quais essas operações podem pertencer estão expressas em:
I. Contadores tendem a visualizar retrospectivamente as finanças da empresa.
II. A abordagem contábil visa fornecer e utilizar valores que representem a eficiência da utilização dos recursos no processo produtivo.
III. Os custos econômicos são aqueles medidos em termos de valores pagos por uma firma na aquisição de seus insumos de produção (os chamados “custos históricos”).
IV. A abordagem econômica foca os chamados “custos de oportunidade”.
V. Custos contábeis não incluem custos implícitos.
No tocante às diferenças entre as abordagens econômica e contábil-financeira dos custos, é correto o que consta APENAS em: